At Risk: Storage Failover Test
Scheduled Maintenance Report for Digital Craftsmen
Completed
Good Evening All,

The controller failover test has been completed on our Enfield Storage Node with a Success.

We have observed no downtime from an external point of view via monitoring and via our own testing.

If you did perceive any issues please don't hesitate to get in touch with us at support@digitalcraftsmen.com.

Kind Regards
Rhodri Metcalfe Davies

Infrastructure Systems Admin

T +44 (0)20 3745 7706
Coppergate House|10 Whites Row|London|E1 7NF
Posted Jun 06, 2023 - 23:24 BST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 06, 2023 - 22:45 BST
Scheduled
Good Morning All,

On Tuesday 6th of June 2023, we will be running through a failover test with one of our storage nodes in the Enfield Datacenter.

This is a simple test to confirm if failover works as intended between the 2 controllers and we do not expect any issues to arise, however due to the nature of the task and components involved, this will be considered as an At Risk maintenance.

If you have any questions or concerns, please don't hesitate to raise a ticket with us by emailing support@digitalcraftsmen.com.

Kind Regards
Rhodri Metcalfe Davies

Infrastructure Systems Admin

T +44 (0)20 3745 7706
Coppergate House|10 Whites Row|London|E1 7NF
Posted Jun 05, 2023 - 10:30 BST
This scheduled maintenance affected: Locations (Enfield Datacentre) and Infrastructure (Storage Cloud).